2016 Road Maintenance and Improvement Projects 

2016 Motor Fuel Tax Resurfacing Project
The general scope of work includes spot curb/gutter repairs, spot sidewalk repairs, and the removal and replacement of the asphalt roadway.  Additionally, the project includes miscellaneous pavement patching throughout the Village and pavement marking refreshing in various locations as well.  The estimated project cost is $1.07 million.    

This project will involve the resurfacing of approximately 3.0 miles of roadway, including:

Canterbury Lane (Edgewood-Clarendon)
Clarendon Lane (Canterbury-Geneva)
Patton Drive (Woodridge-Wainwright)
Foxglove Street (Juneberry-Janeswood)
Juneberry Avenue (Sumac-Foxglove)
Sumac Street (Juneberry-Janeswood)
Mitchell Drive (Westmoreland-Westmoreland)
Stonewall Avenue (End-Jackson)
Perry Drive (Stonewall-Jackson)
Cambridge Lane (Janes-End)
Buckingham Circle (Cambridge-Yorkshire)
Yorkshire Drive (Cambridge-71st)
Armstrong Court (Roberts-End)
Walnut Avenue (End-Mitchell)
Wolfe Drive (Hobson-Lee)
Westgate Court (Wolfe-End)
Eastgate Court (Wolfe-End)
Hobson Road (Village Limit-End)  

This project is scheduled to begin the week of June 13, 2016.
 

2015 (2016 Construction Season) Community Block Development Grant Resurfacing Project
This project will involve the resurfacing of Scenicwood Lane (Elm-Edgewood) and Elm Avenue (Scenicwood-Edgewood).  The general scope of work includes spot curb/gutter repairs, spot sidewalk repairs, and the removal and replacement of the asphalt roadway.  

This project is scheduled to begin in mid-July, 2016.

 

2016 Crack Sealing and Seal Coating Project
This project will include the installation of curb line crack fill on roadways resurfaced during the 2015 construction season (approximately 3.1 miles) and random crack sealing on various roadways throughout the Village (approximately 3.8 miles).  Additionally, the project includes seal coating of approximately 2.9 miles of bike paths, including paths along the following roadways, Parkside Drive (Meyer-Parkside), Double Eagle Drive (Golf Course-Signature Events), Woodridge Drive (Fire Station-Hobson), Hobson Road (Woodridge-ComEd Property), Woodward Avenue (Country Club Condos-83rd), 83rd Street (Woodward-Parkview), and Internationale Parkway (Woodward-I355).  

2016 Pavement Patching Project
The scope of work for this project includes miscellaneous patches throughout the Village.  

Woodridge Drive Resurfacing Project
This project will consist of the removal and replacement of the existing pavement on Woodridge Drive from 75th Street to Center Drive.  Spot repairs to the curb/gutter and sidewalk, installation of additional storm sewer to improve drainage, and median improvements are also included in the scope of the project.  

This project is scheduled to begin June/July 2016.
 

83rd Street Resurfacing Project
This is a joint project with the City of Darien that the Village of Woodridge is leading.  It will include the removal and replacement of the existing pavement on 83rd Street from Janes Avenue to Lemont Road, excluding the bridge deck over I355 (approximately 1.4 miles).  The scope also includes spot repairs to the curb/gutter and sidewalk.  

This project is scheduled to begin in mid-August, 2016.
 

83rd Street and Woodridge Drive Intersection Improvements
The project will make improvements to the north leg of the intersection.  This leg of the roadway will be widened to allow for the creation of an exclusive left turn lane and a thru/right turn lane for southbound traffic on Woodridge Drive.   

This project is scheduled to begin in mid-July, 2016.


Future Projects

• Internationale Parkway (Beaudin to Woodward) – Anticipated Summer 2018 or 2019
• Woodward Avenue (I55 Bridge to Internationale) – Anticipated Summer 2017

Current Road Conditions in Illinois
The Illinois Department of Transportation (IDOT) offers a website that provides current weather conditions, construction projects, and other helpful information relating to Illinois roads and highways